Kimanis Power Dua’s plant commissioning delayed; RAM Ratings to maintain close monitoring of completion progress

Published on 18 Nov 2026.

Share Tweet Email

RAM Ratings is closely monitoring the completion progress of Kimanis Power (Dua) Sdn Bhd’s (KPSB2 or the Company) 100 MW gas-fired power plant in Kimanis, Sabah, which was originally scheduled to commence commercial operations on 1 June 2026. This has now been delayed beyond RAM’s initial three-month delay tolerance, which envisaged plant operations to commence by 1 September 2026. 

KPSB2’s RM580 mil Sukuk Wakalah Facility (2026/2046) is rated AA1/Stable. The rating incorporates an uplift, reflecting our view that Petronas Gas Berhad (PGB), is ‘highly likely’ to provide support beyond its contractual obligations, if necessary, given its role as the transaction’s principal sponsor and the Project’s strategic importance to PGB’s expansion in Sabah.

Overall construction progress stood at 86.6% as at end-October 2026, with delays attributed to prolonged regulatory approvals for certain construction materials, logistical disruptions arising from the Middle East conflict and adverse weather conditions. Management has revised the targeted commercial operation dates (COD) for both Blocks 1 and 2 to end-December 2026. The Project is currently progressing through pre-commissioning activities, although significant milestones, including back-charging and energisation of the PMU substation, remain outstanding before COD can be achieved.

The Company is working closely with Sabah Electricity Sdn Bhd (SESB) on commissioning and testing. The independent technical adviser (ITA), however, views the targeted CODs as challenging, although acceleration measures could help expedite completion, including the concurrent commissioning of gas engines and the deferral of certain commissioning tests until after COD. As the plant is expected to operate intermittently as a peaking facility, the remaining tests can be conducted during non-operating periods.  

As at end-September 2026, KPSB2 had RM248.0 mil in its Disbursement Account against remaining construction costs of about RM236.0 mil. KPSB2 also exercised its step-in rights under the engineering, procurement, construction and commissioning (EPCC) contract to bring the project back on schedule and expedite critical activities. Costs incurred under the step-in arrangement are being tracked and will be offset against future milestone payments to the EPCC contractors. While the contractors have agreed to this arrangement in principle, the final amount has yet to be finalised as the main focus is to expedite the completion of the Project.

During this time, the transaction can draw on the existing contingency sums and available liquidity reserves, including the RM27.1 mil of project contingency, cash balances in the in the Liquidity Support Account (LSA, RM25.0 mil) and the Finance Service Reserve Account (RM27.0 mil). Including the RM41.6 mil of LDs from the EPCC contractors (which is supported by a RM100 mil bank guarantee), these remain sufficient to cover the net maximum delay liquidated damages (LDs) of RM39.4 mil payable to SESB under the power purchase agreement (PPA), as well as the RM26.8 mil aggregate profit obligations due in the next six months and the first principal payment, provided that costs incurred under the step-in arrangement are fully offset against sums payable to the EPCC contractors.

Based on RAM’s sensitised cash flow, any further delay in plant commissioning beyond 1 February 2027 could narrow KPSB2’s liquidity headroom, particularly if LD recoveries fall short of assumptions or step-in costs cannot be fully offset against amounts payable under the EPCC contract. If so, this would increase reliance on additional shareholder liquidity support, either directly or through the replenishment of the LSA via Kimanis Power Sdn Bhd, to preserve the debt service coverage commensurate with the rating.

Under the PPA, a delay beyond 180 days from the scheduled COD, i.e. 28 November 2026, constitutes a termination event, which KPSB2 is seeking to redress; SESB’s approval for KPSB2’s request to extend the PPA’s permitted delay period to 240 days is still pending. RAM views the risk of termination as remote given the Project’s advanced stage of completion and important contribution to stabilise and support Sabah’s energy grid. RAM will continue to monitor the remaining project activity for progress toward eventual COD and confirmation of SESB’s decision on KPSB2’s request for COD extension. Any further or material delays to completion progress beyond January 2027 without additional liquidity support could exert pressure on the rating.

 

Analytical contacts
L Nurisya Abdullah 
(603) 2708 8238
nurisya@ram.com.my

Tan Yan Choong
(603) 2708 8256
yanchoong@ram.com.my

Media contact
Sakinah Arifin
(603) 2708 8212
sakinah@ram.com.my

 

The credit rating is not a recommendation to purchase, sell or hold a security, inasmuch as it does not comment on the security’s market price or its suitability for a particular investor, nor does it involve any audit by RAM Ratings. The credit rating also does not reflect the legality and enforceability of financial obligations.

RAM Ratings receives compensation for its rating services, normally paid by the issuers of such securities or the rated entity, and sometimes third parties participating in marketing the securities, insurers, guarantors, other obligors, underwriters, etc. The receipt of this compensation has no influence on RAM Ratings’ credit opinions or other analytical processes. In all instances, RAM Ratings is committed to preserving the objectivity, integrity and independence of its ratings. Rating fees are communicated to clients prior to the issuance of rating opinions. While RAM Ratings reserves the right to disseminate the ratings, it receives no payment for doing so, except for subscriptions to its publications.

Similarly, the disclaimers above also apply to RAM Ratings’ credit-related analyses and commentaries, where relevant.

Published by RAM Rating Services Berhad
© Copyright 2026 by RAM Rating Services Berhad



Loading...